Progress is ongoing on Kelvington's capital project, the Kelvindell Lodge.

Over the summer, renovation work was focused on completing a kitchen and dining area, which is expected to be running as of September 26.

In the meantime, staff and equipment are being moved from the old hospital site in order to be ready for the change over.

Work will then be turned towards the completion of the east wing at the lodge, which is expected to be finished in late November.

The last part of construction will be renovations to the front entrance, dining room and dementia wing. That work is expected to be complete in March.

Work began on the revamped health care facility in October 2014.